4/20/2010 - Special Board MeetingTHAMES VALLEY DISTRICT SCHOOL BOARD
SPECIAL BOARD MEETING,PUBLIC SESSION
2010 APRIL 20,7:00 P.M.
BOARD ROOM,EDUCATION CENTRE
AGENDA
V-verbal
M -material
1. CALL TO ORDER V
M
2.APPROVAL OF AGENDA
3.REPORTS OF DESIGN COMMITTEES M
a.Proposed New North Ingersoll Public School
b.Proposed Addition and Renovation to Harris Heights Public School
c.Proposed Addition and Renovation to Princess Anne Public School
(Ingersoll)
d.Proposed Addition and Renovation to Edward Street Public School
e.Proposed Addition and Renovation to Locke's Public School
f.Proposed Addition and Renovation to DM Sutherland Public School
g. Proposed Additionand Renovationto Springbank PublicSchool
4.ADJOURNMENT
THAMES VALLEY DISTRICT SCHOOL BOARD
SPECIAL MEETING,PUBLIC SESSION
2010 APRIL 20
The Boardmet inspecial session on 2010 April 20 inthe BoardRoomat the Education Centre, meetingin
public session from 7:08 p.m. to 9:46 p.m. The following were in attendance:
TRUSTEES
J.Bennett S.Peters
S.Doub 8.Polhill
F.Exiey T.Roberts
T.Grant P.Sattler
G.Hart J.Stewart
W.Huff R.Tisdale
C.Neville
Regrets:P.Jaffe,J.Kamphuis
ADMINISTRATION AND OTHERS
B.Tucker
K.Dalton
B.Greene
S.Hughes
M.E.Smith
B.Sonier
P.Tufts
K.Bushell
S.Christie
J.Marlborough
1.CALL TO ORDER.
Board Chair T.Roberts called the meeting to order at 7:08 p.m.
2.APPROVAL OF AGENDA
The agenda was approved on motion of T. Grant,seconded byJ.Stewart.
3.REPORTS OF DESIGN COMMITTEE
Chair Roberts introduced Executive Officer K.Bushell to update the Board on seven design
presentations.Exec. OfficerBushell described the workofthe Design Committees and the approval
process through the Ministry of Education. He noted that within five to seven years enrolment
projections are expected to be met inthe new schools.Aswell,each JK/SK area is designed to have
separate coat and cubby rooms and a storage room.Washrooms are designed in each room,as well
as water table centre.The Boards'standards do not provide a separate lunchroom.
a.Proposed New North Ingersoll Public School
Exec. OfficerBushell indicated that the Board approved on 2009 December 15 forAdministration
to plan a New North Ingersoll Public School and to report back to the Board with respect to:
detailed plans;
•funding;
estimated cost/budget;
schedule.
After the Board received the ARC #13 Report,the Board approved a recommendation to begin
the design process for the New North Ingersoll Public School.As recommended in the ARC
Report,a design committee was formed comprised of community representatives from Princess
Elizabeth,Beachville and Harris Heights Public Schools,the Superintendent of Education forthis
area.Princess Elizabeth and Beachville Principals and teaching staff,the Executive Officer of
Facility Services and Capital Planning and Project Coordinator.The committee worked with
Dickson Partnership Incorporated Architects to develop the proposed plan.
2010 April 20...2
3.REPORTS OF DESIGN COMMITTEES -cont'd
a.Proposed New North Ingersoll Public School -cont'd
During the past four months, design committee meetings were held to receive inputand refine
the proposed design.The proposed design was presented to the school communities on 2010
April 07. The reception from the school communities has been excellent. The process to-date
has been very beneficial and has resulted in a plan that meets the needs of students,staff and
the community.
The new school is to be constructed on the comer of Wonham Street North and Innes Street as
previously approved by the Board.
PROJECT OVERVIEW
Project Synopsis
The objective of this project is to create a new JK-8 Elementary School to accommodate pupils
as designated in the ARC Report.The design committee utilized program standards developed
by Board administration in the design.
The on-the-ground capacity (OTG)will be 615. This capacity matches the enrolment projection
for the proposed school.
The proposed school would be a two storey facility of approximately 58,900 FP and would
include 19 classrooms,5 JK/SK classrooms,a General Arts Room,Gymnasium,Activity Room,
Stage,Library Resource Centre,Developmental Centre,Learning Support Room and
administrative areas.
Site Development
The site will include 52 parking spaces,bus and student drop-off area,as well as asphalt and
grass playing surfaces.The site is adjacent to an existing publicpark and a Joint Use Agreement
will be developed to ensure maximum public use of the combined park and school site.
Energy Efficiency Measures
The new school incorporates a number of measures to address sustainability and the efficient
use of energy,including;
high qualitywindow systems,which reduce heat gain and loss while providing natural light
throughout
•upgraded insulation factors inwalls and roof
• an energy efficient water source heat pump which allows "free heating" of the perimeter of
the building areas using energy obtained from cooling the building core areas
the use of energy recovery wheels which pre-heat ventilation air in the winter using waste
heat fromthe exhaust air system,and pre-cool ventilationairinthe summer byrejecting heat
into the exhaust air system
• ultra efficient condensing hot water heating and domestic boilers
low flow plumbing fixtures
occupancy sensors to turn lights offand set back temperature setpoints when rooms are
unoccupied
The building will be a LEED school silver equivalent in keeping with Ministry of Education
expectations.
MINISTRY OF EDUCATION PUPIL ACCOMMODATION GRANT
The funding of this project is contingent upon receiving a Ministry of Education Pupil
AccommodationGrants. This projectwas submitted tothe Ministry for funding inthe Fall of2009
under the Capita! PrioritiesTemplate and we are optimisticthat funding for this project will be
approved in the near future.
2010 April 20...3
3.REPORTS OF DESIGN COIWWIITTEES -cont'd
a.Proposed New North Ingersoll Public School -cont'd
APPROVAL PROCESS
Board Approval of Tender
A recommendation for the award of the construction contract will be presented to the Board at
the completion of the tendering process.
Ministry of Education Proiect Approval
As detailed in Ministry of Education Memo SB-12,dated April 28,2008,the Board is required to
receive Ministry approval when utilizing any Pupil Accommodation Grants or transfer of Reserve
Funds for a Capital project, prior to awarding the construction contract.The appropriate
submission to the Ministry will be completed once tender results and Board approval have been
finalized.
ESTIMATED COST/BUDGET
Site Purchase and Development $160,000
Design and Construction $11,234,300
Disbursements including permits $150,000
Furniture &Equipment
$514.400
TOTAL $12,058,700
Exec.Officer Bushell introduced Project Coordinator P.Schepens,N.Hindmarsh,and Architect
Lance Dickson.Supt.B.Sonier introduced Principals L.D'Ambrose and B. Reid,Teacher L.
Waton,and Community Representatives Susie Macauley and Sherri Young.Supt.Sonier
expressed thanks to the Design Committee,community representatives,teaching staff,and
custodial staff for their time and effort taken to attend meetings and share dialogue.
Architect Lance Dickson described the new North Ingersoll school site including,site design,
building layouts,and exterior design.Community Representatives S.Macauley and S. Young
expressed their appreciation for the efforts of the design committee and for taking the community
needs and requests into consideration.
Exec.Officer Bushell and Architect Dickson advised that a future addition has been taken Into
account with three classrooms on the first floor and three classrooms on the second floor.Exec.
Officer Bushell noted that with the full-day learning program,standards for capacity have changed
withJK/SK classrooms being loaded at 26 students rather than 20.All gymnasium designs meet
the Board's standards.
Exec.Officer Bushell advised that there are plans for special education space at Harris Heights
as well. He noted that three of the last four schools built have been attached to a public park area
and each municipality has slightlydifferent joint use agreements;however, they are essentially
the same which allows for sharing of parking and space.
He advised that joint agreements generally stipulate that grass cutting and snow plowing are
completed separately as the municipality standards may differ from the Boards'standards,
however, the agreements have the flexibility to be modified as needed.
RECOMMENDATIONS
1.That the Board approve the attached design,budget,and tentative schedule forthe proposed
new north Ingersoll public school.
2.That Administration proceed to tender the proposed new north Ingersoll public school
pending receipt of Ministryof Education approval to construct the project.
2010 April 20...4
3.REPORTS OF DESIGN COWIWIITTEES -cont'd
a.Proposed New North Ingersoll Public School -cont'd
Recommendations 1 and 2 were approved on motionof J Stewart,seconded byG Hart.
Trustee Hartthanked the architectural firm forthe work involved Inthe project.Trustee Stewart
expressed thanks to the Design Committee and community representatives for their work.
b.Proposed Addition and Renovation to Harris Heights Public School
Exec. Officer Bushell noted that the Board approved,on 2009 December 15, for Administration
to plan an addition and renovation to Harris Heights PublicSchool and to report back tothe Board
with respect to:
•detailed plans;
• funding:
•estimated cost/budget;
•schedule.
After the Board received the ARC #13 Report,the Board approved a recommendation to begin
the design process for the addition and renovation to Harris Heights Public School.As
recommended in the ARC Report,a design committee was formed comprised of community
representatives from Harris Heights and Westfield Public Schools,the Superintendent of
Education for this area,Principals and teaching staff from Harris Heights and Westfield Public
Schools,Harris Heights Charge Custodian,the Executive Officer of Facility Services and Capital
Planning and Project Coordinator.Thecommittee worked with DIckson Partnership Incorporated
Architects to develop the proposed plan.
Duringthe past four months, Design Committee meetings were held to receive input and refine
the proposed design.The proposed design was presented to the school communities on 2010
April07.The reception from the school communities has been excellent.The process to date
has been very beneficial and has resulted in a plan that meets the needs of students,staff and
the community.
PROJECT OVERVIEW
Project Synopsis
The objective of this project is to enlarge and renovate the existing JK-8 Elementary Public
School to accommodate pupils as designated inthe ARCReport. The design committee utilized
program standards developed by Board administration inthe design.
The on-the-ground capacity (OTG)will be 602. This capacity matches the enrolment projection
for the proposed consolidated school.
Asinglestorey addition isproposedforthis project,with an area of 17,400 FT®and would include,
5JK/SK classrooms,Gymnasium,Stage and Activity Room. The renovated area would Include,
2 classrooms,Learning Support Room, General Arts Room,Library Resource Centre and
administrative area.
School Renewalcomponents to be addressed inthe existingschool Include window,electrical
services and intercom replacements,HVAC system upgrades and asbestos abatement.The cost
for these components is not includedinthe project estimates and will be funded fromthe School
Renewal,Good Places to Learn and Energy Efficient School grants.
Site Development
The site will include 53 parking spaces and bus and student drop-off area.
2010 April 20...5
3.REPORTS OF DESIGN COMMITTEE -cont'd
b.Proposed Addition and Renovation to Harris Heights Public School -cont'd
PROJECT OVERVIEW -cont'd
MINISTRY OF EDUCATION PUPIL ACCOMMODATION GRANTS
The funding of this project is contingent upon receiving a Ministry of Education Pupil
Accommodation Grants.This project was submitted tothe Ministry forfunding inthe Fall of2009
under the Capital Priorities Template and we are optimistic that funding for this project will be
approved in the near future.
APPROVAL PROCESS
Board Approval of Tender
A recommendation for the award of the construction contract will be presented to the Board at
the completion of the tendering process.
Ministry of Education Project Approval
As detailed in Ministryof Education Memo SB-12,dated April 28,2008,the Board is required to
receive Ministry approval when utilizing any Pupil Accommodation Grants and/or transfer of
Reserve Funds fora Capital project, priorto awarding the construction contract.The appropriate
submission to the Ministry will be completed once tender results and Board approval have been
finalized.
ESTIMATED COST/BUDGET
Design and Construction $4,057,000
Disbursements including permits $150,000
Furniture &Equipment $81.140
TOTAL $4,288,140
Exec. Officer Bushell introduced Lance DIckson,architect for the Harris Heights design and P.
Schepens,the Project Coordinator.Supt.B.Sonier introduced Principals J.Schmalz,N.
Bankes,Vice-Principal K.McCormack,Community Representatives Christine Greeman,June
Nussey and Custodian K. Dumoulin.
Architect DIcksonhighlighted the site design and noted that students will be able to attend at the
school during construction.Community Representative J.Nussey expressed appreciation forthe
efforts of the Design Committee and for taking the community needs and requests into
consideration.
Exec. Officer Bushell noted that whenever asbestos removal is required,itis removed when the
school is unoccupied,e.g. during summer hiatus.All new designs meet barrier free
requirements.Because ramps require a 1-in-12 run and rise,stair lifts are used in some cases.
Buses will line up at the front of the school with eight buses able to be accommodated without
double stacking. If10 buses are on site,only two will require double stacking. Foot traffic flow
was taken into consideration with all new designs.
RECOMMENDATIONS
1.That the Boardapprove the attached design, budget, and tentative schedule forthe proposed
addition and renovation to Harris Heights Public School.
2. That Administration proceed to tenderthe proposed additionand renovationtoHarrisHeights
PublicSchool pending receipt of Ministry of Education approval to construct the project.
Recommendations 1 and 2 were approved on motion G. Hart,seconded byJ. Stewart.
2010 April 20...6
3.REPORTS OF DESIGN COMMITTEE -cont'd
b.Proposed Addition and Renovation to Harris Heights Public School - cont'd
Trustee Stewart expressed thanks tothe DesignCommitteeand community representatives for
their work on the Committee.
c.Proposed Addition and Renovation to Princess Anne Public School (Ingersoll)
The Board approved, on 2009 December 15, for Administration to plan an addition and
renovation to Princess Anne PublicSchool and to report back to the Board with respect to:
detailed plans;
•funding:
•estimated cost/budget;
•schedule.
Afterthe Board received the ARC #13 Report,the Board approved a recommendation to begin
the design process for the addition and renovation to Princess Anne Public School.As
recommended in the ARC Report, a design committee was formed comprised of community
representatives from Princess Anne and Victory Memorial Public Schools,the Superintendent
of Education for this area,Principals and teaching staff from Princess Anne and VictoryMemorial
Public Schools,the Executive Officer of Facility Services and Capital Planning and Project
Coordinator.The committee worked with Dickson Partnership Incorporated Architects to develop
the proposed plan.
During the past four months,design committee meetings were held to receive input and refine
the proposed design.The proposed design was presented to the school communities on 2010
April 07.The reception from the school communities has been excellent.The process to date
has been very beneficial and has resulted Ina plan that meets the needs of students,staff and
the community.
PROJECT OVERVIEW
Project Synopsis
The objective of this project is to enlarge and renovate the existing JK-6 Elementary Public
School to accommodate pupils as designated in the ARC Report and create a JK-8 Elementary
Public School.The design committee utilized program standards developed by Board
administration in the design.
The on-the-ground capacity (OTG)will be 412. This capacity matches the enrolment projection
for the proposed consolidated school.
Asingle storey addition is proposed forthis project withan area of 23,500 FT^and would include
9classrooms,JK/SKclassroom,General Arts Classroom,Gymnasium,Stage and Activity Room.
The renovated area would Include 2 classrooms,Learning Support Room and administrative
area.
School Renewal components to be addressed Inthe existing school include window,fire alarm
and intercom replacements,HVAC system upgrades and room finishes. The cost for these
components is not included inthe project estimates and will be funded fromthe School Renewal,
Good Places to Learn and Energy Efficient Schools grants.
Site Development:
With the expansion of the site as previouslyapproved by the Board, the site will include 42
parking spaces and student drop-off area.
2010 April 20...7
3.REPORTS OF DESIGN COWIWIITTEE -cont'd
0.Proposed Addition and Renovation to Princess Anne Pubiic Schooi (ingersoli)- cont'd
PROJECT OVERVIEW -cont'd
MINISTRY OF EDUCATION PUPIL ACCOMMODATION GRANTS
The funding of this project is contingent upon receiving a Ministry of Education Pupii
Accommodation Grants.This project was submitted tothe Ministry forfunding inthe Faiiof2009
under the Capitai PrioritiesTemplate and we are optimisticthat funding for this project will be
approved in the near future.
APPROVAL PROCESS
Board Approval of Tender
A recommendation for the award of the construction contract will be presented to the Board at
the completion of the tendering process.
Ministryof Education Project Approval
As detailed in Ministry of Education Memo SB-12,dated April 28,2008,the Board is required to
receive Ministry approval when utilizing any Pupil Accommodation Grants and/or transfer of
Reserve Funds for a Capital project, priorto awarding the construction contract.The appropriate
submission to the Ministry will be completed once tender results and Board approval have been
finalized.
ESTIMATED COST/BUDGET
Site Expansion $210,000
Design and Construction $5,737,800
Disbursements Including permits $100,000
Furniture &Equipment $114.756
TOTAL $6,162,556
Exec. OfficerBushell introduced Project Manager J. Attard. Supt. B.Sonier introduced Principals
A.M. Luce and K.Waud,Community Representatives Melanie Everest and Caroline Fitzgerald
and Teacher Marty Vollmershausen.
Architect DicI<son highlighted the site design and noted that this site will be inhabited during
construction.
Community Representatives M.Everest and Caroline Fitzgerald expressed appreciation forthe
efforts of the Design Committee and for taking the community needs and requests into
consideration.It was noted that the existing JK/SK classrooms contain the water table.
Staff and parents have been informed ofa proposed plan to accommodate students during the
construction and this will be presented at the 2010 April 27 Board meeting.
RECOMiUIENDATIONS
1.That the Boardapprove the attached design, budget,and tentative schedule forthe proposed
addition and renovation to Princess Anne Public School.
2.That Administration proceed to tenderthe proposed additionand renovation to Princess Anne
Public School pending receipt of Ministry of Education approval to construct the project.
Recommendations 1 and 2 were approved on motion of J Stewart,seconded by G Hart.
Trustee Stewart expressed thanks to the design committee and community representatives.
2010 April 20...8
3.REPORTS OF DESIGN COMMITTEE -cont'd
d.Proposed Addition and Renovation to Edward Street Public School
The Board approved,on 2009 December 15 forAdministrationto planan addition and renovation
to Edward Street Public School and to report back to the Board with respect to:
•detailed plans;
• funding:
•estimated cost/budget;
•schedule.
Afterthe Board received the ARC #15 Report,the Board approved a recommendation to begin
the design process for the addition and renovation to Edward Street Public School.As
recommended in the ARC Report, a design committee was formed comprised of community
representatives from Edward Street,Balaclava Street and Scott Street Public Schools,the
Superintendent of Education for this area,Principals and teaching staff from Edward Street,
Balaclava Street and Scott Street Public Schools,Edward Street Charge Custodian,the
Executive Officer of Facility Services and Capital Planning and Project Coordinator.The
committee worked with Cornerstone Architecture Incorporated to develop the proposed plan.
During the past four months,design committee meetings were held to receive input and refine
the proposed design.The proposed design was presented to the school communities on 2010
April 15.The reception from the school communities has been excellent.The process to date
has been very beneficial and has resulted in a plan that meets the needs of students,staff and
the community.
PROJECT OVERVIEW
Project Synopsis
The objective of this project is to enlarge and renovate the existing JK-6 Elementary School to
accommodate pupils as designated in the ARC Report and create a JK-8 Elementary school.
The design committee utilized program standards developed by Board administration in the
design.
The on-the-ground capacity (OTG)will be 392.This capacity matches the enrolment projection
for the proposed consolidated school.
Atwo storey addition is proposed forthis project, with an area of 23,940 FP and would include
5 classrooms,4 JK/SK classrooms,Gymnasium,Stage and Activity Room.The renovated area
would include the General Arts Room,the Library Resource Centre,Learning Support Room and
administrative area.
School Renewal components to be addressed in the existing school include electrical service
replacement,asbestos abatement,HVAC system upgrades,boiler replacement and room
finishes.The cost for these components is not included in the project estimate and will be funded
from the School Renewal,Good Places to Learn and Energy Efficient Schools Grants.
Site Development - The site will include 40 parking spaces,bus and student drop-off area.
MINISTRY OF EDUCATION PUPIL ACCOMMODATION GRANTS
The funding of this project is contingent upon receiving a Ministry of Education Pupil
Accommodation Grants.This project was submitted to the Ministryforfunding in the Fall of2009
under the Capital Priorities Template and we are optimistic that funding for this project will be
approved in the near future.
2010 April 20...9
3.REPORTS OF DESIGN COMMITTEE -cont'd
d.Proposed Addition and Renovation to Edward Street Public School -cont'd
PROJECT OVERVIEW -cont'd
APPROVAL PROCESS
Board Approval of Tender
A recommendation for the award of the construction contract will be presented to the Board at
the completion of the tendering process.
Ministryof Education Project Approval
As detailed in Ministry of Education Memo SB-12,dated April 28,2008,the Board Isrequired to
receive Ministry approval when utilizing any Pupil Accommodation Grants and/or transfer of
Reserve Funds fora Capital project, priorto awarding the construction contract.The appropriate
submission to the Ministry will be completed once tender results and Board approval have been
finalized.
ESTIMATED COST/BUDGET
Design and Construction $5,104,422
Disbursements including permits $100,000
Furniture &Equipment $97,750
TOTAL $5,302,172
Exec. OfficerBushell introduced Architect Alison Hannayand ProjectCoordinatorChariieAttard.
Supt. S.Hughes introduced Principal D.Clar who expressed the excitement for this project by
the community and students.Exec. Officer Bushell noted the ravine area will be fenced off.
RECOMMENDATIONS
1.That the board approve the attached design,budget, and tentative schedule forthe proposed
addition and renovation to Edward Street Public School.
2.That administration proceed to tender the proposed addition and renovation to Edward Street
Public School pending receipt of Ministry of Education approval to construct the project.
Recommendations 1 and 2 were approved on motion of T. Grant,seconded byS.Polhill.
Trustees Grant and Exiey expressed thanks to the design committee and community
representatives.
e.Proposed Addition and Renovation to Locke's Public School
The Board approved,on 2009 December 15, for Administration to plan an addition and
renovation to Locke's Public School and to report back to the Board with respect to:
•detailed plans;
•funding;
estimated cost/budget;
schedule.
After the Board received the ARC #15 Report,the Board approved a recommendation to begin
the design process for the addition and renovation to Locke's Public School.As recommended
in the ARC Report,a design committee was formed comprised of community representatives
from Locke's and Edward Street Public Schools,the Superintendent of Education for this area.
Principals and teaching staff from Locke's and Edward Street Public Schools,Locke's Public
School Charge Custodian,the Executive Officer of Facility Services and Capital Planning and
Project Coordinator.The committee worked with Cornerstone Architecture Incorporated to
develop the proposed plan.
2010 April 20...10
3.REPORTS OF DESIGN COWIWIITTEE -cont'd
e.Proposed Addition and Renovation to Locke's Pubiic School -cont'd
During the past four months, design committee meetings were held to receive inputand refine
the proposed design.The proposed design was presented to the school communities on 2010
Aprii 15.The reception fromthe school communities has been excellent. The process to date
has been very beneficial and has resulted Ina plan that meets the needs of students,staff and
the community.
PROJECT OVERVIEW
Project Synopsis
The objective of this project is to enlarge and renovate the existing JK-8 Elementary Public
School to accommodate pupils as designated inthe ARC Report. The design committee utilized
program standards developed by Board administration in the design.
The on-the-ground capacity (OTG)will be 567. This capacity matches the enrolment projection
for the proposed consolidated school.
A single storey addition is proposed for this project with an area of 14,715 FP and would include
6 classrooms,Gymnasium,Stage and Activity Room.The renovated area would include 2
classrooms,5 JK/SK classrooms,the Library Resource Centre,Special Education Classroom,
Learning Support Room and administrative area.
School Renewal components tobe addressed inthe existing school includewindow replacement,
HVAC system upgrades,fire alarm system replacement and room finishes. The cost for these
components is not included in the project estimates and will be funded from the School Renewal,
Good Places to Learn and Energy Efficient Schools grants.
Site Development
The site will include a bus and student drop-off area.
MINISTRY OF EDUCATION PUPIL ACCOMMODATION GRANTS
The funding of this project is contingent upon receiving a Ministry of Education Pupil
Accommodation Grants.This project was submitted tothe Ministry forfunding In the Fall of2009
under the Capital Priorities Template and we are optimistic that funding for this project will be
approved in the near future.
APPROVAL PROCESS
Board Approval of Tender
A recommendation for the award of the construction contract will be presented to the Board at
the completion of the tendering process.
Ministryof Education Project Approval
As detailed in Ministryof Education MemoSB-12,dated April 28,2008,the Board is required to
receive Ministry approval when utilizing any Pupil Accommodation Grants and/or transfer of
Reserve Funds fora Capital project, priorto awarding the construction contract.The appropriate
submission to the Ministry will be completed once tender results and Board approval have been
finalized.
ESTIMATED COST/BUDGET
Design and Construction $4,668,195
Disbursements including permits $100,000
Fumiture &Equipment $80.876
TOTAL $4,849,071
2010 April 20...11
3.REPORTS OF DESIGN COWIWIITTEE -cont'd
e.Proposed Addition and Renovation to Locke's Public School -cont'd
Exec. Officer Bushell noted that C. Attard is the Project Manager. Supt. Hughes introduced
Principal David Westaway who expressed appreciation tothe DesignCommittee on behalfofthe
communityand students.Architect Hannay highlighted the design and site plan.
RECOMMENDATIONS
1.That the Board approve the attached design, budget, and tentative schedule forthe proposed
addition and renovation to Locke's Public School.
2.That Administration proceed to tenderthe proposed addition and renovation to Locke's Public
School pendingreceiptof Ministry of Educationapprovalto construct the project.
Recommendations 1 and 2 were approved on motionof F.Exiey,seconded byT. Grant.
Trustee Exiey expressed thanks to the design committee and community representatives.
f.Proposed Addition and Renovation to P.M.Sutherland Public School
The Boardapproved,on2009 November24,for Administration toplanan additionand renovation
to D.M.Sutherland Public School and to report back to the Board with respect to:
•detailed plans;
• funding:
•estimated cost/budget;
•schedule.
Afterthe Board received the ARC#14 Report.the Board approved a recommendation to begin
the design process for the addition and renovation to D.M.Sutherland Public School.As
recommended in the ARC Report, a design committee was formed comprised of community
representatives from D.M.Sutherland and Hillcrest Public Schools,the Superintendent of
Education for this area,Principals and teaching staff from D.M.Sutherland and Hillcrest Public
Schools,D.M.Sutherland Charge Custodian,the Executive Officer of Facility Services and
Capital Planning and Project Coordinator.The committee worked with Malhotra Nicholson
Sheffield Architects Inc. to develop the proposed plan.
During the past four months,Design Committee meetings were held to receive input and refine
the proposed design.The proposed design was presented to the school communities on 2010
April 14. The reception from the school communities has been excellent. The process to date
has been very beneficial and has resulted in a plan that meets the needs of students,staff and
the community.
PROJECT OVERVIEW
Project Synopsis
The objective of this project is to enlarge and renovate the existing JK-8 Elementary Public
School to accommodate pupils as designated In the ARC Report.The Design Committee utilized
program standards developed by Board administration in the design.
The on-the-ground capacity (OTG)will be 407.This capacity matches the enrolment projection
for the proposed consolidated school.
2010 April 20...12
3.REPORTS OF DESIGN COMMITTEE -cont'd
f.Proposed Addition and Renovation to D.M.Sutherland Public School - cont'd
PROJECT OVERVIEW,Project Synopsis -cont'd
Asingle storey addition is proposed forthis project, withan area of 16,932 FP and would Include
4 classrooms,JK/SK classroom,2 Special Education Classrooms,Gymnasium.Stage and
Activity Room. The renovated area would include, the Library Resource Centre,General Arts
Room,Learning Support Room and administrative area.
School Renewal components tobe addressed inthe existingschool include HVAC,firealarmand
P.A.system replacement and room finishes. The cost for these components is not included in
the project estimate and will be funded from the School Renewal, Good Places to Learn and
Energy Efficient Schools grants.
Site Development -The site will include 40 parking spaces,student drop-off area.
MINISTRY OF EDUCATION PUPIL ACCOMMODATION GRANTS
The funding of this project is contingent upon receiving a Ministry of Education Pupil
Accommodation Grants. Thisprojectwas submitted tothe Ministry forfundinginthe Fall of2009
under the Capital Priorities Template and we are optimisticthat fundingfor this project will be
approved in the near future.
APPROVAL PROCESS
Board Approval of Tender
A recommendation for the award of the construction contract wil!be presented to the Board at
the completion of the tendering process.
Ministryof Education Project Approval
As detailed in Ministry of Education Memo SB-12,dated April 28,2008,the Board is required to
receive Ministry approval when utilizing any Pupil Accommodation Grants and/or transfer of
Reserve Funds fora Capital project, priorto awarding the construction contract.The appropriate
submission to the Ministry will be completed once tender results and Board approval liave been
finalized.
ESTIMATED COST/BUDGET
Design and Construction $4,304,450
Disbursements including permits $100,000
Furniture &Equipment $78.500
TOTAL $4,482,960
Exec. OfficerBushell noted the existing baseball diamond will be lost due to the placement ofthe
newgymnasium. HeIntroducedArchitectJimSheffieldand ProjectCoordinator Kevin McMurray
Super.M.E.Smithintroduced PrincipalsS. Davisand I.Ferrara and Community Representative
Michelle Gall.Architect Sheffield highlighted the design and site plan.
Exec.Officer Bushell introduced Architect Jim Sheffield and Project Coordinator KevinMcMurray
Super.M.E. Smith introduced Principals Susan Davis and Iggy Ferrara and Community
Representative Michelle Gall.ArchitectSheffield highlighted the design and site plan.Principal
Davisand Community Representative M.Gall expressed appreciation to the DesignCommittee
on behalf of the community and students.
2010 April 20...13
3.REPORTS OF DESIGN COMMITTEE -cont'd
f.Proposed Addition and Renovation to D.M.Sutherland Public School -cont'd
RECOMMENDATIONS
1.That the board approve the attached design,budget,and tentative schedule for the proposed
addition and renovation to D.iVI.Sutherland Public School.
2.That administration proceed to tender the proposed addition and renovation to D.M.
Sutherland Public School pending receipt of Ministryof Education approval to construct the
project.
Recommendations 1 and 2 were approved on motion of G. Hart,seconded by J.Stewart.
Trustee Stewart expressed thanks to the design committee and community representatives.
g.Proposed Addition and Renovation to Springbanlc Public School
The Board approved,on 2009 November24,forAdministrationto planan addition and renovation
to Springbank Public School and to report back to the Board with respect to:
detailed plans;
funding;
•estimated cost/budget;
•schedule.
After the Board received the ARC #14 Report,the Board approved a recommendation to begin
the design process for the addition and renovation to Springbank Public School. As
recommended in the ARC Report, a design committee was formed comprised of community
representatives fromSpringbank and Hlllcrest PublicSchools, the Superintendent of Education
for this area,Principals and teaching staff from Springbank and Hillcrest Public Schools,
Springbank Public School Charge Custodian, the Executive Officer of Facility Services and
Capital Planning and Project Coordinator. The committee worked with Malhotra Nicholson
Sheffield Architects to develop the proposed plan.
During the past four months, design committee meetings were held to receive inputand refine
the proposed design.The proposed design was presented to the school communities on 2010
April 14. The reception fromthe school communities has been excellent. The process to date
has been very beneficial and has resulted in a plan that meets the needs of students,staff and
the community.
PROJECT OVERVIEW
Project Synopsis
The objective of this project is to enlarge and renovate the existing JK-8 Elementary Public
School to accommodate pupils as designated inthe ARCReport. The DesignCommittee utilized
program standards developed by Board administration inthe design.
The on-the-ground capacity (OTG)will be 366. This capacity matches the enrolment projection
for the proposed consolidated school.
Asinglestorey addition Isproposedforthis project,with an area of 13,360 FT^and would include
4 classrooms,Gymnasium,Stage and Activity Room. The renovated area would include,JK/SK
classroom, 2 classrooms,the Library Resource Centre, General Arts Room, LearningSupport
Room and administrative area.
2010 April 20...14
3.REPORTS OF DESIGN COIUIIVIITTEE -cont'd
g.Proposed Addition and Renovation to Sprlngbank Public School -cont'd
PROJECT OVERVIEW,Project Synopsis -cont'd
School Renewal components to be addressed inthe existing school Includewindow replacement,
fire alarm replacement,HVAC system upgrades and room finishes.The cost for these
components is not included in the project estimates and will be funded from the School Renewal,
Good Places to Learn and Energy Efficient Schools grants.
Site Development -The development of a bus and student drop-off area is proposed.
MINISTRY OF EDUCATION PUPIL ACCOiVIMODATION GRANTS
The funding of this project is contingent upon receiving a Ministry of Education Pupil
Accommodation Grants.This project was submitted to the Ministryfor funding in the Fall of2009
under the Capital Priorities Template and we are optimistic that funding for this project will be
approved in the near future.
APPROVAL PROCESS
Board Approval of Tender
A recommendation for the award of the construction contract will be presented to the Board at
the completion of the tendering process.
Ministry of Education Project Approval
As detailed in Ministryof Education Memo SB-12,dated April 28,2008,the Board is required to
receive Ministry approval when utilizing any Pupil Accommodation Grants and/or transfer of
Reserve Funds fora Capital project, priorto awarding the construction contract.The appropriate
submission to the Ministry will be completed once tender results and Board approval have been
finalized.
ESTIMATED COST/BUDGET
Design and Construction $3,629,579
Disbursements including permits $100,000
Furniture &Equipment $66.780
TOTAL $3,796,359
Principal Ferrara expressed appreciation to the Design Committee on behalf of the community
and students.
Exec.Officer Bushell noted they have been In contact with the City of Woodstock regarding bus
and student drop-off.He also noted that all new construction meets barrier free building codes
It was noted that the addition has been designed in such a way that if necessary -an addition
could be added at back of gym in the future.
Exec.Officer Bushell noted funding sources are available now for energy efficient schools,
utilizing school renewal funds.The general estimate for the cost of renewal is approximately five
to six million dollars.He introduced Project Manager Ed Clarke.Architect Sheffield highlighted
the design and site plan.
RECOn/IMENDATIONS
1.That the Board approve the attached design,budget,and tentative schedule for the proposed
addition and renovation to Sprlngbank Public School.
2.That Administration proceed to tender the proposed addition and renovation to Sprlngbank
Public School pending receipt of Ministryof Education approval to construct the project.
2010 April 20...15
3.
4.
REPORTS OF DESIGN COMMITTEE -cont'd
g.Proposed Addition and Renovation to Springbanic Public School - cont'd
Recommendations 1 and 2 were approved on motionof J. Stewart,seconded byG. Hart.
Trustees Bennett and Hart expressed her appreciation to ail ofthe Design Committees for their
worl<on their respective projects.
Chair Roberts and Director Tucker expressed appreciation and thanks to Manager Bushell,
Facility Services, parents, communitiesand all design committeesfortheir extraordinary efforts
and work on these projects.
ADJOURNMENT
The meeting adjourned at 9:46 p.m. on motionof J. Stewart,seconded byC.Neville.
Confirmed:
Chairperson
2010 April 20...16
SUMMARY OF APPROVED RECOMMENDATIONS OF 2010 April 20
Thatthe Board approvethe attached design,budget,and tentative schedule for the proposednew
north Ingersoll public school.
That Administration proceedtotendertheproposednew north Ingersoll public school pending receipt
of Ministry of Education approval to construct the project.
Thatthe Board approvetheattacheddesign,budget,and tentative schedule forthe proposed addition
and renovation to Harris Heights Public School.
That Administration proceed totender the proposed addition and renovation to Harris Heights Public
School pendingreceiptof Ministry of Education approvalto construct the project
Thatthe Board approvetheattacheddesign,budget,and tentative schedulefortheproposedaddition
and renovation to Princess Anne Public School.
That Administration proceedtotender the proposed addition and renovation toPrincess Anne Public
School pending receipt of Ministry of Education approval to construct the project.
Thatthe Boardapprovetheattached design, budget,andtentativeschedule forthe proposed addition
and renovation to Edward Street Public School.
That Administration proceed totender the proposed addition and renovation to Edward Street Public
School pending receipt of Ministry of Education approval to construct the project.
Thatthe Boardapprovetheattached design,budget,and tentativeschedule forthe proposed addition
and renovation to Locke's Public School.
That Administration proceedtotender the proposed addition and renovation toLocke's Public School
pending receipt of Ministry of Education approval to construct the project.
Thatthe Boardapprovetheattached design,budget,and tentativeschedule forthe proposed addition
and renovation to P.M.Sutherland Public School.
That Administration proceedto tenderthe proposed addition and renovation to D.M.Sutherland Public
School pending receipt of Ministry of Education approval to construct the project.
Thatthe Board approvetheattacheddesign,budget,and tentative schedulefortheproposedaddition
and renovation to Springbank Public School.
That Administration proceed to tender the proposed addition and renovation to Springbank Public
School pending receipt of Ministry of Education approval to construct the project.